Notifications
You must be signed in to change notification settings - Fork 3
Project Management
This chapter talks about how the project was managed to communicate between the group members
The project was supervised using kanban GitHub project management, kanban is a project management method that is used to manage any size of a workgroup and presenting the roles and tasks that needed to be done during the work period. The Project page on Github was used to manage each aspect of the project as follows:
- The SatRot-Electronics manages the electronics aspects of the product development.
- The SatRot - Telecommunications manages the Antenna, Radio DSP and anything dealing with telecom development.
- The SatRot-Software used for the code developement management, issue tracking, task assignment and general scheduling.
- The SatRot-Mechanical to manage any mechanical aspects of the project and for the motors and the design of the structures.
- SatRot-Taking everyone to space this manages the integration of all the different aspects into a unified system.
Also the ISSUES page is used to present any issues faced in the development of the project and communicate on how it can be resolved, each problem appears with a label to indicate the kind of issue, such as bug for a software issue and so on.
The time and the milestones of the project was monitored using a Gantt chart timeline as shown below
Milestone | Feature | Status |
---|---|---|
0.0 | planning & systems setup | completed |
1.0 | api implementation | completed |
2.0 | webview for Map | completed |
3.0 | http file download from api | completed |
4.0 | get user long and lat location automatically and manually | completed |
5.0 | get sat data | completed |
see other milestones on the milestones tab
SatRot - Taking everyone to space!!!