Group 04 OPTIMUM FIVE RAM IT: ITRO’s ChatBot & Ticketing System

apcjqaloya edited this page Jul 1, 2023 · 183 revisions

Table of Contents

Project Title

RAM-IT: ITRO'S ChatBot and Ticketing System

Project Members

Project Professor

NAME

POSITION

EMAIL

Jose Eugenio L. Quesada

PROJMAN Professor

[email protected]

Project Adviser

NAME

POSITION

EMAIL

Jo Anne M. de la Cuesta

PROJMAN Adviser

[email protected]

Project Team

NAME

EMAIL

Jayson Aloya

[email protected]

Jan Gabriel Prion

[email protected]

John Christopher Langcauon

[email protected]

Marc Julian Sajul

[email protected]

Marc Zamora

[email protected]

Company Profile

Brief Background:

Asia Pacific College (APC) is a private college that promotes itself to those aspiring to attain world-class education with a strong IT-based foundation. Asia Pacific College is a school that can provide access to IT laboratories, school computers, multimedia studio, computer network, and internet connection. This enhances the quality of education and widens the learning opportunities for the students and other members of the APC academic community. Information Technology Resource Office (ITRO) is a department in APC that manages all the IT related aspects within the organization. The ITRO provides services that are specialized in assisting and managing the IT systems, devices, infrastructure, and cybersecurity. It is a customer support department available for all the members of APC community. To inquire for assistance, APC Community Members can set an appointment through email in a Microsoft outlook account or personally contacting any available ITRO staff member inside the school premises.

Business Case

Executive Summary

This business case will tackle on business concerns regarding the proponents proposed project RAM-IT, business concerns like, the benefits of the project, the recommendations that the proponents can bring, the justifications to give importance to why the project is needed for the specific problem it is trying to solve. This document will also have information regarding the current details in its development cycle, for example, the milestones, the performance, the constraints, and the assumptions.

Issue

APC’s ITRO has been able to handle inquiries ever since its establishment in the school, whether it was through their Outlook E-mail or through In-person inquiring. It was fully accepted by the community, but there are still some lacking capabilities with their existing methods on handling inquiries like:

  • Being unable to provide support or answer inquiries in a time efficient manner due to unavailability of the ITRO staff because of demanding and abundant workload.
  • Being unable to delegate, organize, and track the progress of current and incoming inquiries.
  • Having no tracking mechanism on the priority levels of the inquiries that may be given to them that can lead to FAQs being answered one-by-one instead of the staff focusing more on specific concerns that need their attention.
  • Anticipated Outcomes

    Once the ITRO has implemented RAM-IT as a system for managing and handling their inquiries, it will enable them to have a faster way on handling FAQs through the chatbot, they will be able to answer the urgent and high-priority tasks with the priority feature, and they will also have the data like records, and reports be available to them in the system. This will also benefit APC and the community as it enables them to have their inquiries answered promptly and effectively. The end state of this project is for the system to be fully implemented in the ITRO and the APC community using this system for their inquiries and concerns.

    Recommendation

    There are types of technology that can solve business problems, but the proponents have decided that a ticketing system with a chatbot feature will be the optimal choice. This is because it enables the ITRO to have a better and more efficient way of handling FAQs through the chatbot having prompted answers for frequent concerns that come from the community. A more effective way of handling specific concerns that are asked online is through the ticketing system and its chat feature in which the inquirer can communicate with an ITRO staff via chat. This also assists them in managing these inquiries, in terms of delegation of tasks and prioritizing the urgent concerns. It also enables them to have records and reports to give them data regarding the concerns that they face and how abundant they are given a span of time which are all available and displayed in the system.

    Justification

    RAM-IT should be implemented as a system that enables ITRO to handle and manage inquiries, because it improves efficiency in terms of time and method of answering inquiries. Helpdesks and/or ticketing systems have been implemented in numerous companies and schools because they are helpful on enabling their respective technical offices on managing their inquiries, as well as have the inquirers having a designated platform to track and send their inquiries to the ITRO. It should also be implemented as the system can be further improved upon by the ITRO, for example, adding more features that are present in other existing ticketing systems that may benefit the project. The unique feature about RAM-IT is that it enables an efficient communication for two kinds of questions whether it be frequently asked questions which are answered through the chatbot if the inquiry is present there or specific questions which are addressed by the ITRO and will be communicated with them through the chat feature.

    Business Case Analysis Team

    Member Name

    Role

    Role Description

    Jayson Aloya

    Project Manager

    Manages the whole project and leads the project to success. Communicates with Stakeholders and oversees the whole team’s progress. Manages the whole project and leads the project to success. Communicates with Stakeholders and oversees the whole team’s progress.

    Marc Julian Sajul

    Front End Developer

    Programs the UI of RAM-IT

    Marc Zamora

    Back End Developer

    Programs the UX of RAM-IT

    John Christopher T. Langcauon

    Documentation Specialist

    Create the necessary paper deliverables of the project as well as documenting the entire process of completing the project.

    Jan Gabriel Prion

    Documentation Specialist

    Create the necessary paper deliverables of the project as well as documenting the entire process of completing the project.

    Problem Definition

    The ITRO has been handling inquiries regarding technical concerns, concerns can range from password problems, borrowing equipment, and many more. They do this with the use of Microsoft Outlook and allowing students to inquire in-person by visiting the ITRO office. The problem with this method however (especially for online inquiries) is that time for inquiries to be addressed will always vary with the ITRO’s availability. Another problem is that ITRO doesn’t have a method to track all their inquiries all at once in a single page, leading them to always backtrack within their e-mails. Lastly, they are unable to identify if the concerns being given to them are questions that already have answers to them before or specific questions that need their communication to be resolved.

    Problem Statement

    The ITRO has been handling inquiries regarding technical concerns, concerns can range from password problems, borrowing equipment, and many more. They do this with the use of Microsoft Outlook and allowing students to inquire in-person by visiting the ITRO office. The problem with this method however (especially for online inquiries) is that time for inquiries to be addressed will always vary with the ITRO’s availability. Another problem is that ITRO doesn’t have a method to track all their inquiries all at once in a single page, leading them to always backtrack within their e-mails. Lastly, they are unable to identify if the concerns being given to them are questions that already have answers to them before or specific questions that need their communication to be resolved.

    Organizational Impact

    RAM-IT will influence how and where inquiries regarding ITRO will be sent and addressed. It will modify the way ITRO can track, delegate, and address inquiries, as well as make inquiries from APC community members more trackable and easier to follow.

    Existing roles can change as documentation is given an emphasis in the first months of planning, with these developers are adjusted to assist on documentation roles, but later on when the development phase starts, they will continue on with their developer role.

    Technology Migration

    The project overview for RAM-IT provides details regarding the project’s description, objectives, performance, and more details regarding the project’s identity. As the project progresses further into its development phase, these parts will be expounded and/or changed based on the circumstances that will appear when developing the project.

    Project Overview

    The project overview for RAM-IT provides details regarding the project’s description, objectives, performance, and more details regarding the project’s identity. As the project progresses further into its development phase, these parts will be expounded and/or changed based on the circumstances that will appear when developing the project.

    Project Description

    With the ITRO having abundant online inquiries by the HyFlex status of Asia Pacific College, the e-mails that contain inquiries from the members of the APC community might get ignored or be buried by other e-mails, especially if the ITRO staff is not available at that time due to workload that requires them to be elsewhere. ITRO also has a problem where they cannot track the current inquiries that they have started addressing, details like when the inquiry was addressed, solved, and who solved it, these are data that are hard to track in the form of just writing down notes from the taken inquiries in Outlook. The project team had decided that they will create a system where both FAQs and specific inquiries will get answered by the ITRO as soon and as effectively as possible. The team will do this in the form of developing a ticketing system along with features like a display of all tickets, open, pending, and closed, a chatbot where the inquirer can prompt out FAQs and their solutions, notifications, and a ticketing system that comes with a chat, where once inquirers tickets have been accepted, inquirers are allowed to communicate with the ITRO staff assigned to them.

    Goals and Objectives

    These are the following business goals and objectives.

    • Have a system in which ITRO can manage inquiries, track inquiry data, and answer FAQs immediately within the time period of 2 months after the initialization and planning stages.

        o This is the main objective where the team must develop the system that contains all the promised features that were mentioned in previous parts of the business case.

    • Have better ITRO-to-APC community member communication regarding technical inquiries that need to be addressed by the ITRO, 2 months after deployment of the system.

        o The project can create better communication as it also promotes little to no interaction with the chatbot as the chatbot itself can answer frequent inquiries from the APC community members. With this, ITRO staff can focus more on communicating with the ticket submissions and high-priority inquiries and concerns.

    • Have the ticketing system promoted and used across the whole APC community..

    Project Performance

    The following table lists the key resources, processes, or services and their respective business outcomes that will measure the performance of the project.

    Key Resource/Process/Service

    Performance Measure

    Inquiry Response

    The system will be able to help ITRO and inquirers to have a centralized platform resulting to inquirers having more assurance and promptness to be answered.

    Chatbot Feature

    RAM-IT Chatbot will be able to answer 70-90% of the frequently-asked-questions that are sent by the inquirers.

    ITRO Specialists

    With the assigning function, the person delegated to the ticket will have proper knowledge and will be able to assist the inquirer effectively.

    Communication with the ITRO

    The chat feature allows the inquirer and the ITRO to have a better communication line to solve the concern or inquiry.

    Project Assumptions

        •  Resources and budget will be secured for the whole development cycle of the project.

        •  The project team will have the skills and knowledge required to develop the project successfully.

        •  The stakeholders will be able to provide input to further improve the project during its development.

        •  The project with complete features will be tested for approval from the stakeholders and the client.

        •  The project will remain in its scope for the whole duration of the project.

    Project Constraints

    These are all the current constraints that the project is facing. The list will change as the project goes through all the changes during its phases of development.

        •  The project will remain in its scope for the whole duration of the project.

        •  The current project is limited to being a website that can be accessed through Desktop and Mobile by Asia Pacific College community members.

        •  The project requires internet access to be able to use the system.

        •  ITRO’s availability to assist will only be during their business hours.

    Major Project Milestones

    Project Milestone

    Target Date
    (05/28/2024)

    Design Thinking

    04/05/2023

    First Meeting with Project Team

    05/18/2023

    Send Documents for Project Sponsor Approval

    09/01/2023

    Create System Mock-Up

    09/29/2023

    Develop Chat Bot Feature

    11/01/2023

    Develop Ticketing Feature

    11/28/2023

    Implement UI

    03/22/2024

    Training the ITRO

    04/24/2024

    Transferring roles to ITRO

    05/01/2024

    Transferring deliverables to ITRO

    05/08/2024

    Confirmation of Project Completion

    05/28/2024

    Project Complete

    05/28/2024

    Strategic Alignment

    The implementation of RAM-IT aligns with the business goals that the ITRO envisions, this includes:


        •  Efficient Inquiry Response
          o   The system allows for efficiency in terms of time and effectiveness with its chatbot for FAQ responses, and the ticketing system accompanied with the chat feature that allows communication between inquirer and ITROIT specialist.

    The implementation of RAM-IT aligns with the business goals that the ITRO envisions, this includes:


        •  Ticket/Inquiry Trackinge
          o   The system allows the ITRO supervisor and specialists to keep track of the tickets that are open, pending, and closed. It also enables the supervisor to delegate tasks and set the priority levels of the inquiries coming from the members of the APC community.

    Cost Benefit Analysis

    The benefits of the developed project wouldn't be costly due to the client's and the university resources, with the given assistance it will be more than enough for the project to be deployed making it less costly than the other projects. The analysis of the cost will be beneficial to the client and the developers that wouldn't need additional resources that will need financially. Developing the project will not be encountering financial issues.

    Alternative Analysis

    Implementing Signages – During the earlier developments of the project, signages were proposed to accompany the system as it enables people inside APC to view information regarding ITRO, but this was debunked as the project already abundant amounts of features that are unnecessary.


    Having automated delegation – When development was ongoing, the stakeholders proposed that the delegation feature of supervisor to IT specialist can be automated, it was considered by the project team, but it wasn’t aligned with the ITRO’s system of delegation, leading for the idea to be debunked but considered.

    Project Charter

    This charter formally authorizes the RAM-IT: ITRO’s ChatBot & Ticketing System to develop and implement a better way for the ITRO to provide customer support to the APC Community. A project plan will be developed and submitted to the Project Sponsor for approval. The project plan will include: scope statement; schedule; cost estimation; budget; and provisions for scope and limitations, resource, schedule, communications with stakeholders and the sponsor, quality assurance, risk analysis, procurement, and stakeholder management as well as project control. All resources will be assigned by the Project Sponsor, Mr. Jojo F. Castillo, Head of the ITRO.

    RAM-IT: ITRO’s ChatBot and Ticketing System is being developed to assist the ITRO in terms of handling inquiries coming from the members of the APC community. The system will assist them by giving them features like, being able to delegate and track the inquiries in an organized manner, have information on what inquiry has the high priority, and have a ChatBot that can handle FAQs. Members of the APC community will also benefit from this system as they can get their answers immediately if their inquiry can be solved by the ChatBot, if not, they will be assured that the ITRO will see their inquiry with the ticketing system. RAM-IT will be a simple responsive website.

    The Project Manager, Jayson Aloya, is hereby authorized to interface with management as required, negotiate for resources, delegate responsibilities within the framework of the project, and to communicate with all contractors and management, as required, to ensure successful and timely completion of the project. The Project Manager is responsible for developing and creating the project plan, monitoring the schedule, cost, and scope of the project during implementation, and maintaining control over the project by measuring performance and taking corrective action. The project manager will oversee all work and keep track on documentation consistencies. The project manager will lead the project along with the rest of the members towards success.

    The Project Sponsor must approve any schedule changes which may impact milestones. A detailed schedule will be included in the project plan.

    Summary Milestone Schedule – List key project milestones relative to project start.

    Project Milestone

    Target Date
    (05/28/2024)

    Design Thinking

    04/05/2023

    First Meeting with Project Team

    05/18/2023

    Send Documents for Project Sponsor Approval

    09/01/2023

    Create System Mock-Up

    09/29/2023

    Develop Chat Bot Feature

    11/01/2023

    Develop Ticketing Feature

    11/28/2023

    Implement UI

    03/22/2024

    Training the ITRO

    04/24/2024

    Transferring roles to ITRO

    05/01/2024

    Transferring deliverables to ITRO

    05/08/2024

    Confirmation of Project Completion

    05/28/2024

    Project Complete

    05/28/2024

    The budget for this project is detailed below in a table. Costs for this project are categorized in the different phases of the project:

    Manpower Cost Estimate

    Initiation

    ROLE

    Base Monthly Salary (Based on Glassdoor)

    Total Working Hours

    Hourly Rate

    No. of People

    COST

    Project Manager

    ₱ 40,000

    130

    ₱ 230.77

    1

    ₱ 30,000.1

    Documentation Specialist

    ₱ 16,000

    21

    ₱ 92.31

    1

    ₱ 1,938.51

    Documentation Specialist

    ₱ 16,000

    110

    ₱ 92.31

    1

    ₱ 10,154.1

    Front-End Developer

    ₱ 33,500

    -

    ₱193.27

    1

    -

    Back-End Developer

    ₱ 25,000

    -

    ₱144.23

    1

    -

    Sub-Total

    ₱ 42,092.71

    Planning

    ROLE

    Base Monthly Salary (Based on Glassdoor)

    Total Working Hours

    Hourly Rate

    No. of People

    COST

    Project Manager

    ₱ 40,000

    258

    ₱230.77

    1

    ₱ 59,538.66

    Documentation Specialist

    ₱ 16,000

    55

    ₱ 92.31

    1

    ₱ 5,077.05

    Documentation Specialist

    ₱ 16,000

    18

    ₱ 92.31

    1

    ₱1,661.58

    Front-End Developer

    ₱ 33,500

    36

    ₱193.27

    1

    ₱ 6,957.72

    Back-End Developer

    ₱ 25,000

    10

    ₱144.23

    1

    ₱ 1,442.3

    Sub-Total

    ₱ 74,677.31

    Execution

    ROLE

    Base Monthly Salary (Based on Glassdoor)

    Total Working Hours

    Hourly Rate

    No. of People

    COST

    Project Manager

    ₱ 40,000

    64

    ₱ 230.77

    1

    ₱ 14,769.28

    Documentation Specialist

    ₱ 16,000

    22

    ₱ 92.31

    1

    ₱ 2,030.82

    Documentation Specialist

    ₱ 16,000

    110

    ₱ 92.31

    1

    ₱10,154.1

    Front-End Developer

    ₱ 33,500

    664

    ₱193.27

    1

    ₱ 128,331.28

    Back-End Developer

    ₱ 25,000

    504

    ₱144.23

    1

    ₱ 72,691.92

    Sub-Total

    ₱ 227,977.4

    Monitoring & Control

    ROLE

    Base Monthly Salary (Based on Glassdoor)

    Total Working Hours

    Hourly Rate

    No. of People

    COST

    Project Manager

    ₱ 40,000

    170

    ₱ 230.77

    1

    ₱ 39,230.9

    Documentation Specialist

    ₱ 16,000

    18

    ₱ 92.31

    1

    ₱1,661.58

    Documentation Specialist

    ₱ 16,000

    -

    ₱ 92.31

    1

    -

    Front-End Developer

    ₱ 33,500

    360

    ₱193.27

    1

    ₱ 236,562.48

    Back-End Developer

    ₱ 25,000

    -

    ₱144.23

    1

    -

    Sub-Total

    ₱ 277,454.9

    Closeout

    ROLE

    Base Monthly Salary (Based on Glassdoor)

    Total Working Hours

    Hourly Rate

    No. of People

    COST

    Project Manager

    ₱ 40,000

    88

    ₱ 230.77

    1

    ₱ 20,307.76

    Documentation Specialist

    ₱ 16,000

    18

    ₱ 92.31

    1

    ₱1,661.58

    Documentation Specialist

    ₱ 16,000

    -

    ₱ 92.31

    1

    -

    Front-End Developer

    ₱ 33,500

    80

    ₱193.27

    1

    ₱ 17,123.18

    Back-End Developer

    ₱ 25,000

    -

    ₱144.23

    1

    -

    Sub-Total

    ₱ 39,092.52

    Total Manpower Cost

    ₱ 661,294.84

    Contingency Cost

    Contingency Rate Cost (Total Cost * 10%)

    66,129.484

    Project Cost Summary

    Approved Budget

    ₱ 1,500,000.00

    Manpower costs

    ₱ 661,294.84

    Contingency cost

    ₱ 66,129.484

    Total Project Cost

    ₱ 727,424.324

    Stakeholders Management Strategy Plan

    Introduction

    The stakeholder management strategy for RAM-IT: ITRO’s ChatBot & Ticketing System aims to proactively identify, prioritize, engage, and communicate with stakeholders to ensure their needs and expectations are met. The strategy will be integrated into the project management approach, guided by principles of transparency, inclusiveness, and accountability. It will focus on building positive relationships, effective communication, conflict mitigation, and continuous monitoring and evaluation to ensure successful system implementation and operation.The stakeholder management strategy for RAM-IT: ITRO’s ChatBot & Ticketing System aims to proactively identify, prioritize, engage, and communicate with stakeholders to ensure their needs and expectations are met. The strategy will be integrated into the project management approach, guided by principles of transparency, inclusiveness, and accountability. It will focus on building positive relationships, effective communication, conflict mitigation, and continuous monitoring and evaluation to ensure successful system implementation and operation.

    Identify Stakeholders

    RAM-IT: ITRO's Chatbot & Ticketing System employs a stakeholder management strategy that involves identifying and engaging with various parties. These include the ITRO team, responsible for technical implementation and maintenance, comprising the ITRO Supervisor and IT Specialists. School administration, including administrators and staff, oversees system usage and effectiveness. Teachers, counselors, and students interact with the system for technical issues and inquiries. School administrators, board members, officials, and system support providers also have stakeholder roles. Other stakeholders, such as alumni or APC community members, may be involved based on system requirements. Identifying and engaging with these stakeholders ensures their perspectives, needs, and concerns shape the system's management and improvement.

    Key Stakeholders

    Key stakeholders in the ITRO school ticketing system includes:


    Information Technology Resource Office (ITRO):

        •    IT Supervisor

        •    IT Specialist


    Academic Personnel/Administrator(ITRO):

        •    Administrators

        •    Board Members

        •    Teachers

        •    Counselors

    Academic Personnel/Administrator(ITRO):

        •    College Students

        •    Senior High School Students

        •    Alumni

    Project Team:

        •    Optimum Five

    These key stakeholders may require more communication and management throughout the project’s lifecycle, and it is important to identify them to seek their feedback on their desired level of participation and communication. Identifying and engaging with these key stakeholders is crucial to consider their perspectives, needs, and concerns in the management of the ticketing system.

    Stakeholder Analysis


    Stakeholder

    Objectives, Requirements, Interests

    Influence

    Project Contribution

    Resistance

    JoJo Castillo

    (APC ITRO)



    •Objective is to ensure a reliable and user-friendly system that complies with policies and regulations.



    •Knowledge of relevant technologies, experience managing technical systems, and strong communication and problem-solving skills.



    •Interest in meeting the needs of the school community, ensuring data security, maintaining up-to-date knowledge, and contributing to efficient school operations.


    HIGH Relationship with other stakeholders, organizational structure, and project sponsor

    Process improvement, access to resources, and technical expertise

    Resource constraints &

    Concerns about data security

    Academic Personnel & Administrator



    •The objective is to have access to an easy to use, fast, and streamlined ticket management, with accurate data and ticket resolution.



    •Requires the ticketing system to be accessible and can be integrated to school operations.



    •Interest in improved overall experience and reduce delays for technology related inquiries.


    HIGH collected data and user experience

    Providing feedback on its usability, functionality, and effectiveness

    User challenges & Changes to existing processes

    Academic Community



    •Objective is to have a convenient and reliable ticketing system that allows easy access



    •Requires the ticketing system to be ser-friendly, secure, and integrates to daily school activity.



    •Interest in being able to track ticket inquiries and requests.


    Moderate Collected data and user experience

    Providing feedback on its usability, functionality, & effectiveness.

    User challenges & Changes to existing processes

    Optimum Five



    •Objective is to design, develop, and implement a reliable, user-friendly, and efficient system that meets the needs of the school and its stakeholders.



    •Requires gathering and analyze requirements from various stakeholders, including students, parents, teachers, administrators, and IT staff.



    •Interest in the success of the project, as it reflects their skills and expertise, and may be interested in career advancement and gaining experience.




    HIGH

    Project design, development, documentation, management, and implementation





    Project design, development, documentation, management, & implementation





    Technical challenges & Changes to existing processes

    Scope Management Plan

    Introduction

    The RAMIT scope management plan will provide an overview of the best practices and modern instruments that will be used to specify, record, and manage the project's scope. The project team will be able to use agile approaches and real-time collaboration technologies to provide a cutting-edge tool that satisfies the requirements of all the stakeholders that are involved.

    The scope of RAMIT will be defined through the following activities:

    Requirements gathering

    The project team will employ a number of methods to collect and Include user interviews, focus groups, and online surveys while documenting the system's needs.

    User stories

    In order to describe the functionality of the project, the project team will generate user stories. system from the viewpoint of the ultimate user. The order of these stories will be determined by the development process and it will be guided by the business value.

    Verify Scope

    The requirements and user stories will be used as input to verify the scope. It will give a high-level summary of the project scope, including the deliverables, exclusions, and restrictions.

    Control Scope

    By including the verification of the scope, the control scope will be established. project management strategy, as well as the user stories. As the information is updated, the Project progresses to account for scope changes.

    Scope Management Approach

    The scope of RAMIT will be documented in the following ways: 

    Requirements documentation

    The system's specifications will be outlined in a specifications document for requirements.

    Project management plan

    The scope is a component of the project management plan. the scope baseline and any other pertinent details regarding the extent of the project.

    Backlog

    A Backlog will be maintained to track all changes to the scope of the project, including the description of the change, the impact on the project, and the required approvals.

    The scope of RAMIT will be controlled through the following activities:

    Scope verification

    Agile testing methods will be used by the team to ensure that the project's deliverables are compliant with the specifications and follow the stated scope.

    Scope change control

    Project scope modifications will be handled through a formal change control procedure that includes an evaluation of the effect on the Schedule, budget, and quality of the project.

    Scope change review

    Each change request will be the subject of a scope change review. Verify that the change is required, practicable, and in line with the project's goals.

    Roles and Responsibilities

    Name

    Role

    Responsibility

    Jayson Aloya

    Project Manager

    Responsible for leading the team and project to success by ensuring everyone is doing their part to the best quality. Responsible for communicating with the Stakeholders and the Project Sponsor. Responsible for checking if the documents are consistent with one another.

    Marc Julian Sajul

    Front End Developer

    Responsible for the UI and coding of the visuals for RAM-IT.

    Marc Zamora

    Back End Developer

    Responsible for the UX and coding of the features for RAM-IT.

    John Christopher T. Langcauon

    Documentation Specialist

    Responsible for documents made for the project. Responsible for writing the minutes of the meeting. Responsible for compilation of documents.

    Jan Gabriel Prion

    Documentation Specialist

    Responsible for documents made for the project.

    Jojo F. Castillo

    Project Sponsor

    Responsible for approving documents.

    Jo Anne M. de la Cuesta

    Project Adviser

    Responsible for advising the team on decisions. Responsible for checking documents to ensure that everything is consistent with quality and coherence.

    Information Technology Resource Office

    Beneficiary

    Will benefit from RAM-IT as it is made to increase quality and improve their customer services.

    Asia Pacific College Members

    Beneficiary

    Will benefit from the services provided by RAM-IT once implemented by the ITRO.

    Scope Definition

    The Ticketing system can decrease the margin of unsolved problems that aren't solved yet or problems that hasn't seen the light of day. The opportunity to increase the number of these inquiries to be solved by the ITRO by making a system that can sort, centralize, and manage the inquiries in a single system.

    Project Scope Statement

        •    Product Scope Description – project RAM-IT aims to provide the ITRO a better way of providing customer service through a chatbot and ticketing system.

        •    Product Acceptance Criteria – In order for the project to be officially completed, the following acceptance criteria should be met:

        •    Project Deliverables – the project deliverables can be seen in the work breakdown structure. This includes documents and the prototype.

    Work Breakdown Structure

    Scope Verification

    The team will employ agile testing techniques to make sure that the project's deliverables adhere to the specified scope and are in compliance with the requirements. The project team will use various techniques for scope verification to guarantee that the Dispatch Directory System project deliverables satisfy the original scope. These methods include: Quality Checklists : A Backlog will be maintained to track all changes to the scope of the project, including the description of the change, the impact on the project, and the required approvals. Scope Baseline: It will be possible to establish the scope baseline by incorporating the scope declaration. User stories and project management strategy are both involved. The project moves on to take scope adjustments into account as the information is updated.

    Scope Control

    Scope control is the process of monitoring the status of the scope of the project. This section also details the change process for making changes to the scope baseline.

    Cost Management Plan

    Introduction

    For the management of costs for RAM-IT, it will be managed by the Documentation team, which consists of 3 members of the project team, these members will be responsible for reporting and documenting the costs that the team will spend during the development of the project. The Project Leader and Head Developer will have the authority to approve changes made to the project or its budget. The cost performance will be measured using earned value and it will be reported every progress meeting that the proponents will schedule. The proponents will also discuss and propose their budget, costs, and performance with their stakeholders and client.

    Cost Management Approach

    Costs for this project will be managed at the fourth level of the Work Breakdown Structure (WBS). Control Accounts (CA) will be created at this level to track costs. Earned Value calculations for the CA’s will measure and manage the financial performance of the project. Although activity cost estimates are detailed in the work packages, the level of accuracy for cost management is at the fourth level of the WBS. Credit for work will be assigned at the work package level. Work started on work packages will grant that work package with 50% credit; whereas, the remaining 50% is credited upon completion of all work defined in that work package. Costs may be rounded to the nearest dollar and work hours rounded to the nearest whole hour.


    Cost variances of +/- 0.1 in the cost and schedule performance indexes will change the status of the cost to cautionary; as such, those values will be changed to yellow in the project status reports. Cost variances of +/- 0.2 in the cost and schedule performance indexes will change the status of the cost to an alert stage; as such, those values will be changed to red in the project status reports. This will require corrective action from the Project Manager in order to bring the cost and/or schedule performance indexes below the alert level. Corrective actions will require a project change request and be must approved by the Project Sponsor before it can become within the scope of the project.

    Measuring Project Costs

    This section defines how the project’s costs will be measured. RAM-IT focuses on Earned Value Management for measuring and controlling a project’s costs. Earned Value Management is a broad and powerful tool; as such, we recommend that all project managers take some formal courses in Earned Value Management.


    Our example in this section measures four Earned Value measurements; Schedule Variance (SV), Cost Variance (CV), Schedule Performance Index (SPI) and Cost Performance Index (CPI). For most typical projects these four measurements can provide enough insight for effective management without overburdening the Project Manager with Earned Value calculations and measurements.


    Schedule Variance (SV) is a measurement of the schedule performance for a project. It’s calculated by taking the Earned Value (EV) and subtracting the Planned Value (PV). Since EV is the actual value earned in the project and the PV is the value our project plan says we should have earned at this point, when we subtract what we planned from the actual we have a good measurement which tells us if we are ahead or behind the baseline schedule according to our project plan. If SV is zero, then the project is perfectly on schedule. If SV is greater than zero, the project is earning more value than planned thus it’s ahead of schedule. If SV is less than zero, the project is earning less value than planned thus it’s behind schedule.


    Cost Variance (CV) is a measurement of the budget performance for a project. CV is calculated by subtracting Actual Costs (AC) from Earned Value (EV). As we already know, EV is the actual value earned in the project. AC is the actual costs incurred to date, thus when we subtract what our actual costs are from the EV, we have a good measurement which tells us if we are above or below budget. If the CV is zero, then the project is perfectly on budget. If the CV is greater than zero, the project is earning more value than planned thus it’s under budget. If the CV is less than zero, the project is earning less value than planned thus it’s over budget.


    The Schedule Performance Index (SPI) measures the progress achieved against that which was planned. SPI is calculated as EV/PV. If EV is equal to PV, the value of the SPI is 1. If EV is less than the PV then the value is less than 1, which means the project is behind schedule. If EV is greater than the PV the value of the SPI is greater than one, which means the project is ahead of schedule. A well performing project should have its SPI as close to 1 as possible, or maybe even a little under 1.


    The Cost Performance Index (CPI) measures the value of the work completed compared to the actual cost of the work completed. CPI is calculated as EV/AC. If CPI is equal to 1 the project is perfectly on budget. If the CPI is greater than 1 the project is under budget if it’s less than 1 the project is over budget.


    Reporting Format

    The reporting of the cost management plan will be included in the monthly project status report. The Monthly Project Status Report will include a section labeled, “Cost Management”. This section will contain the Earned Value Metrics identified in the previous section. All cost variances outside of the thresholds identified in this Cost Management Pl and will be reported on including any corrective actions which are planned. Change Requests which are triggered based upon project cost overruns will be identified and tracked in this report.


    The reports regarding the cost management plan will be part of the monthly project status report. It will be included in the section labeled “Cost Management”. The delivery of the reports will be curated as accessible and simple to understand for the client, project team, and stakeholders.

    Cost Variance Reponse Process

    The Control Thresholds for this project are a CPI or SPI of less than 0.8 or greater than 1.2. If the project reaches one of these Control Thresholds a Cost Variance Corrective Action Plan is required. The Project Manager will present the Project Sponsor with options for corrective actions within five business days from when the cost variance is first reported. Within three business days from when the Project Sponsor selects a corrective action option, the Project Manager will present the Project Sponsor with a formal Cost Variance Corrective Action Plan. The Cost Variance Corrective Action Plan will detail the actions necessary to bring the project back within budget and how the effectiveness of the actions in the plan will be measured. Upon acceptance of the Cost Variance Corrective Action Plan, it will become a part of the project plan and the project will be updated to reflect the corrective actions.

    Cost Change Control Process

    The cost change control process will follow the established project change request process. Approvals for project budget/cost changes must be approved by the project sponsor.

    Project Budget

    The budget for this project is detailed below. The base monthly salaries are referenced from Glassdoor’s monthly salary rates (Glassdoor, n.d.). Labor costs are based on the log hours (multiplied with the hourly rates) of each member per work package listed in OpenProject. Costs for this project are presented in various categories...

    Manpower Cost Estimate

    Initiation

    ROLE

    Base Monthly Salary (Based on Glassdoor)

    Total Working Hours

    Hourly Rate

    No. of People

    COST

    Project Manager

    ₱ 40,000

    130

    ₱ 230.77

    1

    ₱ 30,000.1

    Documentation Specialist

    ₱ 16,000

    21

    ₱ 92.31

    1

    ₱ 1,938.51

    Documentation Specialist

    ₱ 16,000

    110

    ₱ 92.31

    1

    ₱ 10,154.1

    Front-End Developer

    ₱ 33,500

    -

    ₱193.27

    1

    -

    Back-End Developer

    ₱ 25,000

    -

    ₱144.23

    1

    -

    Sub-Total

    ₱ 42,092.71

    Planning

    ROLE

    Base Monthly Salary (Based on Glassdoor)

    Total Working Hours

    Hourly Rate

    No. of People

    COST

    Project Manager

    ₱ 40,000

    258

    ₱230.77

    1

    ₱ 59,538.66

    Documentation Specialist

    ₱ 16,000

    55

    ₱ 92.31

    1

    ₱ 5,077.05

    Documentation Specialist

    ₱ 16,000

    18

    ₱ 92.31

    1

    ₱1,661.58

    Front-End Developer

    ₱ 33,500

    36

    ₱193.27

    1

    ₱ 6,957.72

    Back-End Developer

    ₱ 25,000

    10

    ₱144.23

    1

    ₱ 1,442.3

    Sub-Total

    ₱ 74,677.31

    Execution

    ROLE

    Base Monthly Salary (Based on Glassdoor)

    Total Working Hours

    Hourly Rate

    No. of People

    COST

    Project Manager

    ₱ 40,000

    64

    ₱ 230.77

    1

    ₱ 14,769.28

    Documentation Specialist

    ₱ 16,000

    22

    ₱ 92.31

    1

    ₱ 2,030.82

    Documentation Specialist

    ₱ 16,000

    110

    ₱ 92.31

    1

    ₱10,154.1

    Front-End Developer

    ₱ 33,500

    664

    ₱193.27

    1

    ₱ 128,331.28

    Back-End Developer

    ₱ 25,000

    504

    ₱144.23

    1

    ₱ 72,691.92

    Sub-Total

    ₱ 227,977.4

    Monitoring & Control

    ROLE

    Base Monthly Salary (Based on Glassdoor)

    Total Working Hours

    Hourly Rate

    No. of People

    COST

    Project Manager

    ₱ 40,000

    170

    ₱ 230.77

    1

    ₱ 39,230.9

    Documentation Specialist

    ₱ 16,000

    18

    ₱ 92.31

    1

    ₱1,661.58

    Documentation Specialist

    ₱ 16,000

    -

    ₱ 92.31

    1

    -

    Front-End Developer

    ₱ 33,500

    360

    ₱193.27

    1

    ₱ 236,562.48

    Back-End Developer

    ₱ 25,000

    -

    ₱144.23

    1

    -

    Sub-Total

    ₱ 277,454.9

    Closeout

    ROLE

    Base Monthly Salary (Based on Glassdoor)

    Total Working Hours

    Hourly Rate

    No. of People

    COST

    Project Manager

    ₱ 40,000

    88

    ₱ 230.77

    1

    ₱ 20,307.76

    Documentation Specialist

    ₱ 16,000

    18

    ₱ 92.31

    1

    ₱1,661.58

    Documentation Specialist

    ₱ 16,000

    -

    ₱ 92.31

    1

    -

    Front-End Developer

    ₱ 33,500

    80

    ₱193.27

    1

    ₱ 17,123.18

    Back-End Developer

    ₱ 25,000

    -

    ₱144.23

    1

    -

    Sub-Total

    ₱ 39,092.52

    Total Manpower Cost

    ₱ 661,294.84

    Contingency Cost

    Contingency Rate Cost (Total Cost * 10%)

    66,129.484

    Project Cost Summary

    Approved Budget

    ₱ 1,500,000.00

    Manpower costs

    ₱ 661,294.84

    Contingency cost

    ₱ 66,129.484

    Total Project Cost

    ₱ 727,424.324

    Schedule Management Plan

    Introduction

    For every project that will be created or built, there is always a record of the time and where the deliverables are placed. Deliverables that are either to be started, ongoing, and complete, here thus also lie the plans for the future of the projects which in the case of a technological project is called either update or upgrade.

    The Schedule Management Plan is technically one of the most important aspects of planning to create a program where it records and even lists deadlines for each part of the project. The purpose of the schedule management plan for technological projects is to complete a specific program in order and thus monitor the insights of the developers in the first place are thoroughly followed.

    Schedule Management Approach

    There is a software called OpenProject, it was introduced and taught to the developers of the project. In OpenProject, there is a Gantt chart where the project team can monitor and assign deliverables, here lies the developers list, plan, and oversees the parts of the project that moves the progress of building the program.

    The said software helps the team to approach the schedule management plan. The developers include a specific format to be easily understood which reviews the progress now and then. This software also indicates the milestones of the project, which under these milestones are deliverables of each member that records the progress, roles, and responsibilities.

    Schedule Control

    With the help of how the developers approached the schedule management plan, the team was able to put the management under control. The team was able to control schedule management not only with the said application but also with the help of Microsoft Teams. Microsoft Teams reminds the members about meetings that tackle the listed plan in the team's OpenProject.

    For the communication and updates that control, and follow the flow of the plan for the project. Microsoft Teams is effective and efficient, and with its Calendar, the team meetings are reminded. Communicating with the team helps the members with their deliverables and deadlines. With this kind of control, it will be easy for the team to be notified if the project has a minor or major update will be added to the project.

    Group or Team meetings are important not only for brainstorming and communicating about the project but also this reminds the team about the schedule management plan of the project.

    Schedule Changes and Thresholds

    As for the team's development progress, there is a consistent and planned schedule since each member of the team must be updated on little by little progress of each work. The team expects that at any time in the progress, there will be multiple circumstances of schedule changes and the deliverables or project thresholds.

    For the team to comply with these kinds of situations, we do not set or stack up the contents and the lists of deliverables from the schedule management plan for that it would be possible and still on track and thus maintain the consistency of the progress of the project if there will be changes from the schedules of each member, deliverables and the deadlines that can also affect the threshold which if managed well, the team will not have a hard time to re-adjust.

    The team allotted minimum of 2 days per week to comply with these circumstances, which will create an additional days with a minimum of 1 week of change in the threshold for the monthly deliverable or milestone of the project.

    Scope Change

    The given allotted dates, times, or days in the team's schedule management plan will not ruin the plan if a change will occur during the progress. It will be less workload for the team and its project manager to readjust or re-baselined the schedule management plan.

    The team consists of a few members, so assigning more deliverables for each day would stack up and may end in confusion or forgetting about the assigned deliverables, it will create havoc within the schedule management plan, depending on the change that will occur.

    The proper management and setting of the schedule management plan will affect the developers, the team, and the project manager that oversees the progress from time to time. It will be easier to monitor, adjust and add if there will be changes within the plan.

    The given preparedness within the schedule management plan is also the scope of the team, although the team expects multiple changes during the progress. As developers, the team must prepare for minor or major adjustments and changes in the schedule management plan.

    Work Breakdown Structure (WBS)

    Introduction

    The Work Breakdown Structure shows the Summary Tasks and Work Packages that are needed to be done through the whole process of the project RAM-IT: ITRO’s ChatBot & Ticketing System.

    Outline View

    1. RAM-IT: ITRO’s ChatBot & Ticketing System
      1.1 Initiation
        1.1.1 Design Thinking
        1.1.2 Create Business Case
        1.1.3 Create Project Charter
        1.1.4 Project Sponsor Approval of Project
        1.1.5 Assign Project Team & Roles
        1.1.6 Identify Stakeholders
      1.2 Planning
        1.2.1 First Meeting with Project Team
        1.2.2 Create Stakeholders Management Strategy Plan
        1.2.3 Create Cost Management Plan
        1.2.4 Create Scope Management Plan
        1.2.5 Create Time Management Plan
        1.2.6 Create Work Breakdown Structure
        1.2.7 Create Human Resource Management Plan
        1.2.8 Create Quality Management Plan
        1.2.9 Create Risk Management Plan
        1.2.10 Create Communications Management Plan
        1.2.11 Create Procurement Management Plan
        1.2.12 Create Implementation Plan
        1.2.13 Create Change Management Plan
        1.2.14 Meeting for Documents Development
        1.2.15 Send Documents for Project Sponsor Approval
      1.3 Execution
        1.3.1 Analysis & Design
          1.3.1.1 Develop Requirements Analysis
          1.3.1.2 Develop System Analysis
          1.3.1.3 Create System Design
          1.3.1.4 Create System Wireframe
          1.3.1.5 Create System Mock-Up
        1.3.2 Development
          1.3.2.1 Develop Log-In Feature
          1.3.2.2 Develop Chat Bot Feature
          1.3.2.3 Develop Ticketing Feature
          1.3.2.4 Develop Notification Feature
          1.3.2.5 Develop Data Report Feature
          1.3.2.6 Develop Filter Feature
          1.3.2.7 Develop Ticket History Feature
          1.3.2.8 Develop Chat Feature
          1.3.2.9 Implement UI
        1.3.3 Testing & Training
          1.3.3.1 Install System
          1.3.3.2 Perform Test Cases
          1.3.3.3 Training the ITRO
      1.4 Monitoring & Control
        1.4.1 Gather Feedback Data
        1.4.2 Risk Manage
        1.4.3 Monitor if Project Deliverables are complying to Project Documents
        1.4.4 Weekly Status Report
      1.5 Completion/Closeout
        1.5.1 Transferring roles to ITRO
        1.5.2 Transferring deliverables to ITRO
        1.5.3 Archiving Documents
        1.5.4 Final Meeting
        1.5.5 Confirmation of User Acceptance
        1.5.6 Confirmation of Project Completion

    Hierarchical Structure

    Level WBS Code Element Name
    1 1 RAM-IT: ITRO's ChatBot & Ticketing System
    2 1.1 Initiation
    3 1.1.1 Design Thinking
    3 1.1.2 Create Business Case
    3 1.1.3 Project Charter
    3 1.1.4 Project Sponsor Approval of Project
    3 1.1.5 Assign Project Team & Roles
    3 1.1.6 Identify Stakeholders
    2 1.2 Planning
    3 1.2.1 First Meeting with Project Team
    3 1.2.2 Create Stakeholders Management Strategy Plan
    3 1.2.3 Create Cost Management Plan
    3 1.2.4 Create Scope Management Plan
    3 1.2.5 Create Time Management Plan
    3 1.2.6 Create Work Breakdown Structure
    3 1.2.7 Create Human Resource Management Plan
    3 1.2.8 Create Quality Management Plan
    3 1.2.9 Create Risk Management Plan
    3 1.2.10 Create Communications Management Plan
    3 1.2.11 Create Procurement Management Plan
    3 1.2.12 Create Implementation Plan
    3 1.2.13 Create Change Management Plan
    3 1.2.14 Meeting for Documents Development
    3 1.2.15 Send Documents for Project Sponsosr Aprroval
    2 1.3 Execution
    3 1.3.1 Analysis & Design
    4 1.3.1.1 Develop Requirements Analysis
    4 1.3.1.2 Develop System Analysis
    4 1.3.1.3 Create System Design
    4 1.3.1.4 Create System Wireframe
    4 1.3.1.5 Create System Mock-Up
    3 1.3.2 Development
    4 1.3.2.1 Develop Log-In Feature
    4 1.3.2.2 Develop Chat Bot Feature
    4 1.3.2.3 Develop Ticketing Feature
    4 1.3.2.4 Develop Notification Feature
    4 1.3.2.5 Develop Data Report Feature
    4 1.3.2.6 Develop Filter Feature
    4 1.3.2.7 Develop Ticket History Feature
    4 1.3.2.8 Develop Chat Feature
    4 1.3.2.9 Implement UI
    3 1.3.3 Testing & Training
    4 1.3.3.1 Install System
    4 1.3.3.2 Perform Test Cases
    4 1.3.3.3 Training the ITRO
    2 1.4 Monitoring & Control
    3 1.4.1 Gather Feedback Data
    3 1.4.2 Risk Manage
    3 1.4.3 Monitor if Project Deliverables are complying to Project Documents
    3 1.4.4 Weekly Status Report
    2 1.5 Completion/Closeout
    3 1.5.1 Transferring roles to ITRO
    3 1.5.2 Transferring deliverables to ITRO
    3 1.5.3 Archiving Documents
    3 1.5.4 Final Meeting
    3 1.5.5 Confirmation of User Acceptance
    3 1.5.6 Confirmation of Project Completion

    Tabular View

    Level 1 Level 2 Level 3 Level 4
    1 RAM-IT: ITRO's ChatBot & Ticketing System 1.1 Initiation 1.1.1 Design Thinking
    1.1.2 Create Business Case
    1.1.3 Create Project Charter
    1.1.4 Project Sponsor Approval of Project
    1.1.5 Assign Project Team & Roles
    1.1.6 Identify Stakeholders
    1.2 Planning 1.2.1 First Meeting with Project Team
    1.2.2 Create Stakeholders Management Strategy Plan
    1.2.3 Create Cost Management Plan
    1.2.4 Create Scope Management Plan
    1.2.5 Create Time Management Plan
    1.2.6 Create Work Breakdown Structure
    1.2.7 Create Human Resource Management Plan
    1.2.8 Create Quality Management Plan
    1.2.9 Create Risk Management Plan
    1.2.10 Create Communications Management Plan
    1.2.11 Create Procurement Management Plan
    1.2.12 Create Implementation Plan
    1.2.13 Create Change Management Plan
    1.2.14 Meeting for Documents Development
    1.2.15 Send Documents for Project Sponsor Approval
    1.3 Execution 1.3.1 Analysis & Design 1.3.1.1 Develop Requirements Analysis
    1.3.1.2 Develop System Analysis
    1.3.1.3 Create System Design
    1.3.1.4 Create System Wireframe
    1.3.1.5 Create System Mock-Up
    1.3.2 Development 1.3.2.1 Develop Log-In Feature
    1.3.2.2 Develop Chat Bot Feature
    1.3.2.3 Develop Ticketing Feature
    1.3.2.4 Develop Notification Feature
    1.3.2.5 Develop Data Report Feature
    1.3.2.6 Develop Filter Feature
    1.3.2.7 Develop Ticket History Feature
    1.3.2.8 Develop Chat Feature
    1.3.2.9 Implement UI
    1.3.3 Testing & Training 1.3.3.1 Install System
    1.3.3.2 Perform Test Cases
    1.3.3.3 Training the ITRO
    1.4 Monitoring & Control 1.4.1 Gather Feedback Data
    1.4.2 Risk Manage
    1.4.3 Monitor if Project Deliverables are complying to Project Documents
    1.4.4 Weekly Status Report
    1.5 Completion/Closeout 1.5.1 Transferring roles to ITRO
    1.5.2 Transferring deliverables to ITRO
    1.5.3 Archiving Documents
    1.5.4 Final Meeting
    1.5.5 Confirmation of User Acceptance
    1.5.6 Confirmation of Project Completion

    Tree Structure View

    WBS Dictionary

    Level WBS Code Element Name Definition
    1 1 RAM-IT: ITRO's ChatBot & Ticketing System The project name for the system being developed to improve the ITRO’s customer service.
    2 1.1 Initiation The phase to start off the project.
    3 1.1.1 Design Thinking The research and brainstorming session of the project team with the help of the project sponsor and stakeholders.
    3 1.1.2 Create Business Case The paper that contains the information about the business/company the project is being made for.
    3 1.1.3 Project Charter The paper that contains information about the project sponsor and project manager along with the information about the project milestones and budget.
    3 1.1.4 Project Sponsor Approval of Project The project manager sends the business case and project charter along with other necessary information about the project to the project sponsor for approval.
    3 1.1.5 Assign Project Team & Roles Finding the right people to join the creation of the project and assigning roles to them.
    3 1.1.6 Identify Stakeholders Identifying the people affected and will benefit from the project.
    2 1.2 Planning The phase where plans are made for project management.
    3 1.2.1 First Meeting with Project Team The meeting that kick starts the whole project.
    3 1.2.2 Create Stakeholders Management Strategy Plan The document that contains the plan on identifying and managing the stakeholders needs for the project.
    3 1.2.3 Create Cost Management Plan The document that contains the budget and costs that will be used for the project.
    3 1.2.4 Create Scope Management Plan The document that provides a clear understanding of what the project limitations are.
    3 1.2.5 Create Time Management Plan The document that provides the schedule of how long the project and the work packages will be done.
    3 1.2.6 Create Work Breakdown Structure Where work packages are labeled through each phases of the project.
    3 1.2.7 Create Human Resource Management Plan The document that plans on how to handle the staffs of the project including the project team and the team that will take over once the project is done.
    3 1.2.8 Create Quality Management Plan The document that assures consistency and quality for each deliverables.
    3 1.2.9 Create Risk Management Plan The document that contains the contingency plans that will be done when a risks occurs.
    3 1.2.10 Create Communications Management Plan The document that manages how information is delegated from project team to stakeholders and project sponsor.
    3 1.2.11 Create Procurement Management Plan The document that handles the resources and where to get them.
    3 1.2.12 Create Implementation Plan The document that contains the plan to implement the project once completed.
    3 1.2.13 Create Change Management Plan The document that shows the procedure on how to apply changes to the plan and also documents the changes throughout the project.
    3 1.2.14 Meeting for Documents Development The meetings done once a week to be able to quality assure each document and to assure that everyone is on the same page.
    3 1.2.15 Send Documents for Project Sponsosr Aprroval All documents are sent to Project Sponsor for approval.
    2 1.3 Execution The phase wherein the plans are ready to be executed.
    3 1.3.1 Analysis & Design This sub-phase where the team creates the structure of how the system will work and how data will be carried throughout the system.
    4 1.3.1.1 Develop Requirements Analysis Developing the tables and diagrams that is required for the project.
    4 1.3.1.2 Develop System Analysis Developing the tables and diagrams on how the system will work.
    4 1.3.1.3 Create System Design Creating a solid design for the system.
    4 1.3.1.4 Create System Wireframe Creating a wireframe on how the system will look like.
    4 1.3.1.5 Create System Mock-Up Visualizing the wireframe.
    3 1.3.2 Development The sub-phase where the system is developed.
    4 1.3.2.1 Develop Log-In Feature Developing the feature to be able to log-in and connecting it to the database for accounts.
    4 1.3.2.2 Develop Chat Bot Feature Developing the features for the chat bot and its responses.
    4 1.3.2.3 Develop Ticketing Feature Developing the system for the ticketing feature.
    4 1.3.2.4 Develop Notification Feature Developing the notifications feature.
    4 1.3.2.5 Develop Data Report Feature Developing a feature that analyzes raw data into useful information used in reports.
    4 1.3.2.6 Develop Filter Feature Developing a search feature.
    4 1.3.2.7 Develop Ticket History Feature Developing an archive for ticket history.
    4 1.3.2.8 Develop Chat Feature Developing a chat system for the customer and service provider to communicate.
    4 1.3.2.9 Implement UI Implementing visual and user friendly UI.
    3 1.3.3 Testing & Training The sub-phase to test the system and train the people that will be handling the system once passed over.
    4 1.3.3.1 Install System Installing the system to the ITRO.
    4 1.3.3.2 Perform Test Cases Testing the system.
    4 1.3.3.3 Training the ITRO Training the people that will handle the system once passed over.
    2 1.4 Monitoring & Control The phase that goes along with the execution phase where monitoring and controlling of the project is done.
    3 1.4.1 Gather Feedback Data Gathering feedback data to improve the system.
    3 1.4.2 Risk Manage Managing risks that occurs.
    3 1.4.3 Monitor if Project Deliverables are complying to Project Documents Monitoring the project deliverables and quality assuring them.
    3 1.4.4 Weekly Status Report A weekly meeting that reports the status of the project to the Project Sponsor and Stakeholders.
    2 1.5 Completion/Closeout The final phase of the project.
    3 1.5.1 Transferring roles to ITRO Officially passing over the system to the ITRO.
    3 1.5.2 Transferring deliverables to ITRO Passing over the deliverables of the project to the ITRO.
    3 1.5.3 Archiving Documents Archiving the documents for further references and projects.
    3 1.5.4 Final Meeting The final meeting for everyone involved in the project.
    3 1.5.5 Confirmation of User Acceptance Assuring that every stakeholder needs are met.
    3 1.5.6 Confirmation of Project Completion The official conclusion of the project.

    Glossary of Terms

    Level of Effort: Level of Effort (LOE) is how much work is required to complete a task.

    WBS Code: A unique identifier assigned to each element in a Work Breakdown Structure for the purpose of designating the elements hierarchical location within the WBS.

    Work Package: A Work Package is a deliverable or work component at the lowest level of its WBS branch.

    WBS Component: A component of a WBS which is located at any level. It can be a Work Package or a WBS Element as there's no restriction on what a WBS Component is.

    WBS Element: A WBS Element is a single WBS component and its associated attributes located anywhere within a WBS. A WBS Element can contain work, or it can contain other WBS Elements or Work Packages.