User story
Dependent on the outcome of the BGE blending research stories, as a stakeholder (Matt M) I would like the post-blending BGE purposes and Limber pipeline. This pipeline is covered as pipeline 6 in the BGE lucid chart.
Who are the primary contacts for this story
Matt M, Sara W, Ben T, Katy T
Who is the nominated tester for UAT
Matt M, Sara W
Acceptance criteria
To be considered successful the solution must allow:
If Limber blending is completed the pipeline 6 section of the lucid chart should be added to the BGE pipeline.
If Limber blending is discarded the end of the ISC pipeline should be added onto the BGE pipeline.
Dependencies
This story is blocked by the following dependencies:
User story
Dependent on the outcome of the BGE blending research stories, as a stakeholder (Matt M) I would like the post-blending BGE purposes and Limber pipeline. This pipeline is covered as
pipeline 6
in the BGE lucid chart.Who are the primary contacts for this story
Matt M, Sara W, Ben T, Katy T
Who is the nominated tester for UAT
Matt M, Sara W
Acceptance criteria
To be considered successful the solution must allow:
Dependencies
This story is blocked by the following dependencies: