Hi, I have no idea what the task Ruler is. If this is a question about the Tasks plugin, please read the following page thoroughly. If you still have a question, I will need some information to be able to help.
|
Beta Was this translation helpful? Give feedback.
2 replies
Sign up for free
to join this conversation on GitHub.
Already have an account?
Sign in to comment
-
Hello,
in adding a due date and then having the note reflected in the task Ruler the task is recurrent until the selected date.
Only using scheduled the task is reported only on the due date.
How to make the task with a due date to show up only at the selected date?