MS7 End of ComCam Assembly, Integration & Test #4
Comments
Change request C017 |
25/AUG/21
|
27/AUG/21
|
1 similar comment
27/AUG/21
|
Change request C028, approved at 23/SEP/21 Exec Group Meeting moved due date from PM23 (31/MAY/2021) to PM41 (30/NOV/22). |
16/NOV/22
|
Exec meeting on 28/NOV/22 approved Change Request C057 that stated this milestone corresponds to the Rubin Project supporting milestone : "SITCOM-105 : ComCam + PF re-Installed on TMA". According DMTN-232 dated 05/JAN/23, the due date is 17/JUL/23 (LSST:UK PM49). |
24/AUG/23
|
10/JAN/24 According to RubinObs-Digest Vol 44, Issue 1 (recvd via email on 15/NOV/23) ,
SITCOM-105 was announced as done at the December'23 SITCOM meeting but DMTN-232 still to be updated. Exec group have said MS7 will remain open until DMTN-232 updated. |
14/FEB/24 |
08/MAY/24
|
04/JUN/24
|
14/NOV/24
|
Verification check as listed in the Milestones spreadsheet is "Communication from LSST Project".
Exec meeting on 28/NOV/22 approved Change Request C057 that stated this milestone corresponds to the Rubin Project supporting milestone : "SITCOM-105 : ComCam + PF re-Installed on TMA", the date of which can be found in DMTN-232
The text was updated successfully, but these errors were encountered: