Change request C061 explains how this deliverable is due sixteen months after the LSST:UK milestone MS13 (#16)which in turn is directly linked to the Rubin Project top milestone : COMC-0654-0430 Due date will therefore change according to COMC-0654-0430. See DMTN-232 Celebratory Milestones at https://dmtn-232.lsst.io/ for dates.
The text was updated successfully, but these errors were encountered:
Change request C061 approved at 20/FEB/23 Exec Group mtg.
C061 explains how this deliverable is due sixteen months after the LSST:UK milestone MS13 which in turn is directly linked to the Rubin Project top milestone : COMC-0654-0430 Due date will therefore change according to COMC-0654-0430. See DMTN-232 Celebratory Milestones at https://dmtn-232.lsst.io/ for dates.
Change request C061 explains how this deliverable is due sixteen months after the LSST:UK milestone MS13 (#16)which in turn is directly linked to the Rubin Project top milestone : COMC-0654-0430 Due date will therefore change according to COMC-0654-0430. See DMTN-232 Celebratory Milestones at https://dmtn-232.lsst.io/ for dates.
The text was updated successfully, but these errors were encountered: