- Ernest Shackleton
- 🕐 PM1(Mar.9) - RM(Apr.4)
- Scrum Master: IP
- closed since last RM
- resolved (FB) since last RM
- opened
- Product Backlog (PO view)
- Sprint Scrum Wall (Developers view)
- NEW sprint wall (developers view)
- Activity: sprint-PRs and sprint-MRs
- AWS cluster (us-east-1)
- staging_aws (Testers only - changelogs)
- production_aws (changelogs)
- Z43 cluster (ch-zh)
- staging_z43 (Testers only - changelogs)
- production_z43 (changelogs)
- master (ch-zh) (Developers only)
PO | Topic | Title | Presenter | Status | Duration | Start-Time |
---|---|---|---|---|---|---|
5 | file-system | #513 M5 Filesystem integration | 10:05 | |||
1 | #580 osparc-fs: Internals |
MaG | Ongoing | 3' | ||
2 | #578 osparc-fs: Hardware |
DK | Ongoing | 3' | ||
5 | #579 osparc-fs: Remote Mounts |
Paused | ||||
3 | scheduler | #349 S-D25.4 Simulation framework SCHEDULER Y4M05 | SAN, ALL | Ongoing | 10' | 10:11 |
19 | #350 S-D25.5 Simulation Framework resource allocation Y4M05 |
Ongoing | ||||
4 | s4l web | #519 M1–12 Enhancements of the modeling/simulator/postpro service and framework | CR, MaG | Ongoing | 14' | 10:21 |
6 | meta | #353 S-D22.2 Meta-Modeling sensitivity analysis Y4M08 | PC | Done | 8' | 10:35 |
7 | #354 S-D22.3 Meta-Modeling uncertainty assessment Y4M10 |
Done | ||||
8 | #515 M6 Support for unit conversion and detection of compatible ports |
OM | Ongoing | 4' | 10:43 | |
9 | #355 S-D22.4 Meta-Modeling optimizer module Y4M12 |
Ongoing | ||||
16 | control | #510 M4 Modular platform for the generation and exploration of control strategies | EI | Ongoing | 8' | 10:47 |
9 | #555 Coupling API |
Ongoing | ||||
12 | TI | #91 TI Planning | OM | Ongoing | 3' | 10:55 |
13 | UI/UX, support | #546, #517 oSPARC UI/UX: Team Black and Support | OM | Ongoing | 8' | 10:58 |
integration | #522 M5 Extend/Create onboarding facilities | Ongoing | ||||
#2409 Service integration (or service onboarding) backlog |
ANE | Ongoing | 1' | 11:06 | ||
15 | #595 Comsol license server |
KZ | Paused | 1' | 11:07 | |
20 | resources | #576 Control, provide, and track resources | SAN | Ongoing | 1' | 11:08 |
17 | maintenance | #428 Maintenance/scaling of the platform | PC | Ongoing | 5' | 11:09 |
18 | #509 M1–9 Cybersecurity and privacy | DK | Ongoing | 2' | 11:14 | |
21 | #545 Portal work | IP | Ongoing | 1' | 11:16 | |
22 | #26 support onboarding of SPARC computational models, S-D1, Y3M1-12 | KZ | Ongoing | 1' | 11:17 | |
devops | #529 M1–12 DevOps: platform monitoring and maintenance; fixing of stability issues; down-time reduction | ALL, DK | Ongoing | 5' | 11:18 |
- Paused: this issue was not scheduled/skipped for this sprint
- In Progress: this issue is still under development
- Resolved: no more work left to do on this issue. PO can review an decide to close or reopen.
- Ongoing: a recurrent task
Needs PO update, see previous reviews
Needs PO update, see previous reviews