Review Meeting - 2020/07/31 @10:00

Agenda

Issue Title Presenter Status Duration Start Time
#266 HW/SW Dev Support Case: Online Material Database for Solid Materials IP Done 10 min 11:15
#68 Everybody at z43 uses osparc. S4L Notebooks S4L: CR In progress 0 min 11:25
#496 Migration to AWS
Moving from DALCO
ALL In progress 5 min 11:25
#496 Add end2end testing to AWS OM Done 5 min 11:30
#91 TI Treatment Planning MaG In Progress 0 min 11:35
#265 Search & Discover KZ IP In Progress 10 min 11:35
#505
#12
Large Models/Results Rendering & Interaction (M9; D4.a). Video streaming
Postpro workbench; S-D15, Y3M6
S4L: LM In Progress 0 min 11:45
#22 Fine Grained Access Rights S-D6, Y3M6 OM In Progress 5 min 11:45
#264 Simple Sweeper OM In progress 10 min 11:50
#24 Flatmap Widget S-D4, Y3M8 OM Done 5 min 12:00
#232 Team Black [TB-Project Backlog] OM In progress 5 min 12:05
#21 Onboarding of SPARC computational models S-D1 Y3M1-12 KZ In progress 5 min 12:10

Progress

Deliverable Due Title % Done Notes
J-D3 M1 Retreat prep 100 Retreat has taken place
J-D15 M1 Documentation agreement 75 Requirements established
S-D26 M1 Idea Lab subaward 100 The subaward has been setup and preparations are ongoing
S-D2 M2 OpenCOR / CellML module & PMR S-D2, M2 #1069 100 Two approaches to run OpenCOR models or create OpenCOR-based services have been implemented
J-D33 M2 Publication linking, J-D33, Y3M2,8 #33 100 Meta-data sections throughout SIM-CORE support linking to pdf, webpages; awaiting MAP-CORE functionality to automatically surface publications (based on DOI?)
J-D3 M2 Retreat 100
J-D6.a M2 Conference list 100
J-D21 M2 DRC feedback/issue collection and tracking (Infrastructure) - J-D21 #1065 100
J-D28.a M2 Portal testing (Testing and Infrastructure) - J-D28 #1066 100 oSPARC end-to-end testing infrastructure established
J-D7.a M2 simple creation of data-processing modules, S-D7, Y3M2,4,5,2-12 #21 100 survey drafted, work on functionality started
S-D24 M2 UI/UX subaward 100 first phase contracted, ongoing
S-D7a data analysis and visualization 50 survey has been drafted
S-D3g metrics 75 metrics have been selected and prepared for presentation to steering committee
S-D18 M3 NEUROFAUNA rat 75
J-D3e M3 DRC Governance strategies 100
J-D4 M3 slide-decks (marketing material) 100 Worked on it this sprint- should be completed soon
J-D16 ongoing Workshops and webinars 50 one workshop completed, ongoing
J-D20 M3 White paper outlining SPARC data standards and QC metrics for SPARC data depositors 50
J-D29 M3 Data access/cost structure
S-D10 M4 macro/templates, towards guided mode 100
S-D22 M5 AWS 100
S-D12 M5 o2S2PARC API 70
S-D7 b, c M5 simple creation of osparc services 70
S-D20 M5 NEUROCOUPLE Keast team collaboration 20
S-D6 M6 Fine-grained access rights 50 UI Improvements
S-D15 M6 Advanced Postpro 70
S-D5 M7 IT’IS tissue property database 100
S-D17 M7 Neuro Postpro
S-D4 M8 Flatmap Widget
J-D31 M8 Notification Service part 1
S-D3 M9 Grill Approach
S-D4 M9 Notification service parts 2&4
S-D8 M9 UI for Service Submission 50
S-D19 M9 Neurocouple service
S-D21 M1-12 DevOps/Platform stability

Blockers

  • S-D18: decaying rat prevents reimaging required to properly segment the PNS; registration-based approach will be tried, to merge PNS images from previously scanned rat
  • Continuous work on Platform stability is time-consuming but essential work and may delay other milestones
  • S-D20: Martin Bertrand’s work on the detailed pelvic PNS functionalization will be delayed
  • Migration to AWS: High priority tasks related to Z43's energy infrastructure retain our DevOps resources and delay the completion of this one.

TB-Project Backlog