Sitewide V2: Facilities Sprint 1 Plan #17554
Labels
Epic
Issue type
Facilities
Facilities products (VAMC, Vet Center, etc)
Needs refining
Issue status
sitewide
Schedule Notes
Sprint Priorities 🎯
At the end of this sprint, what do we want to have accomplished/delivered?
Tickets for top priority:
UX
DISCUSS tracking ACs / use of epics / tasks.
Front End
DISCUSS: Analytics deadline April 5, Design system deadline for V1 deprecation where V3s exist = May 3. Progress to date indicates we need to focus on V3 adoption to hit date target. Or: push back on DS re: the deadline.
Other FE work
Drupal
DISCUSS: Christian working alone. Daniel or Edmund will need to be pulled in for code reviews. We will need to probably source QA on our team. We should expect a slow down as a result. 13 point suggested load may be high, even without text validation ticket.
Other Drupal work
The text was updated successfully, but these errors were encountered: